Slope stabilization work continues on the north bank of the Peace River for the Site C dam, September 2017. (B.C. Hydro)

UPDATE: Decision time for John Horgan on Site C dam

Energy Minister Michelle Mungall says delaying it is off the table

Premier John Horgan’s cabinet intends to make a decision on whether to continue building the most expensive construction project in B.C. history by the end of 2017.

The B.C. Utilities Commission released its independent report on the project Wednesday, ordered by Horgan to fulfil a promise he has repeated many times since becoming NDP leader.

The BCUC report questions whether Site C can make its 2024 completion date, and concludes the cost “may” exceed $10 billion. It describes the option of suspending work and restarting it in 2024 as the “least attractive of the three scenarios” set out by the government.

Energy Minister Michelle Mungall said Wednesday the report is technical and requires further study, but one thing that is clear is that delaying Site C is not an option that would protect B.C. Hydro ratepayers from unnecessary rate increases.

In the legislature Wednesday, Peace River South MLA Mike Bernier called on the government to make a decision within a month, to provide certainty to the people working at Site C. Eight years of study done under the B.C. Liberal government, and court decisions saying consultation with affected people was adequate, mean no further delay is needed, Bernier said.

Green Party leader Andrew Weaver said the report “should be viewed as the final nail in the coffin of Site C,” due to potential cost overruns and the B.C. Liberal government’s rush to secure fixed-term electricity supply to liquefied natural gas projects.

“The one issue of concern” is the transfer of the $4 billion cost of scrapping Site C to be added to the provincial debt, Weaver said.

Horgan’s government instructed BCUC to come up with cost estimates for completing the dam, pausing construction for a more thorough review of alternatives and future electricity demand, or stopping it and restoring the project area.

The report estimates the cost of shutting down Site C and remediating the project area to be $1.8 billion, plus the cost of finding alternative energy sources to meet demand, on top of the $2 billion already spent.

“The suspension and restart scenario adds at least an additional $3.6 billion to final costs and is by far the most expensive of the three scenarios,” the report states.

The BCUC panel also concluded that “increasingly viable alternative energy sources such as wind, geothermal and industrial curtailment could provide similar benefits to ratepayers as the Site C project with an equal or lower unit energy cost.”

Horgan said Tuesday that one more round of consultation with area Indigenous communities will be conducted next by Indigenous Relations Minister Scott Fraser, and then cabinet will consider its options.

B.C. Hydro has already awarded the major contracts for the powerhouse, river diversion and main civil works in the riverbed.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

6.5-magnitude earthquake in Idaho shakes the Kootenays

An earthquake was reportedly felt just before 5 p.m. throughout parts of B.C. and Alberta

Nelson and COVID-19: everything you need to know

Check this page for every local story related to the outbreak

Burning ban issued for Nelson area

All open burning is prohibited to reduce COVID-19 respiratory risk

It’s time for community gardens

From reader John Northcott

From medical equipment to water treatment, Teck Trail is an essential service

” … Trail operations is one of a few, and in some cases, the only North American supplier.”

B.C. records five new COVID-19 deaths, ‘zero chance’ life will return to normal in April

Province continue to have a recovery rate of about 50 per cent

John Horgan extends B.C.’s state of emergency for COVID-19

Premier urges everyone to follow Dr. Bonnie Henry’s advice

B.C.’s first community COVID-19 death was dentist ‘dedicated’ to health: lawyer

Vincent was 64 when he died on March 22 after attending the Pacific Dental Conference

Two inmates at prison housing Robert Pickton test positive for COVID-19

Correctional Service of Canada did not release any details on the identities of the inmates

COVID-19 case confirmed at restaurant in Cache Creek: Interior Health

Customers who visited the site from March 25 to 27 are asked to self-isolate

BC SPCA launches matching campaign to help vulnerable animals after big donations

Two BC SPCA donors have offered up to $65,000 in matching donations

First COVID-19 outbreak in Interior Health identified at Okanagan agricultural business; 14 cases confirmed

75 workers are in isolation — 63 migrant workers and 12 local workers

Quarantined B.C. mom say pandemic has put special-needs families in ‘crisis mode’

Surrey’s Christine Williams shares family’s challenges, strengths

Anti-tax group calls for MPs, senators to donate scheduled pay raises to charity

Bill C-30, adopted 15 years ago, mandates the salary and allowance increases each calendar year

Most Read