Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Supreme Court of Canada will hear Sinixt appeal May 12

B.C. has appealed Indigenous hunting case through several levels of court starting in Nelson in 2016

Shuttle service at Trail hospital will remain for now

“ … shuttle service will remain in place while work on the new drop-off area … continues.”

Nelson’s Jesse Pineiro named B.C. boxing coach of the year

Pineiro and his fighters from Nelson Boxing Club were honoured at provincials

Fire destroys Fauquier restaurant

Early-morning blaze destroys Mushroom Addition

Salmo RCMP report drug bust

Fentanyl, methamphetamine and cocaine were seized along with Canadian cash

UPDATE: Two killed in fiery collision on Highway 1 near Revelstoke

The Trans Canada Highway was closed for four hours

Father, two children killed after car goes over embankment on B.C. highway

The single vehicle crash occured near Kamloops on Highway 5A

Trout ‘doing quite well’ at Kootenay hatchery after otters, who ate 150 fish, relocated

River otters had been pillaging a moat outside the facility for months, gobbling up about 150 trout

VIDEO: Illicit drug overdoses killed 981 in B.C. in 2019, down 38%

Chief coroner says figures were down about a third in the province’s fourth year of the opioid crisis

Trudeau revisits blackface embarrassment during Black History Month

Photos and a video of Trudeau wearing makeup to darken his skin surfaced during last fall’s election campaign

VIDEO: B.C.’s seventh coronavirus patient at home in Fraser Health region

Canada in ‘containment’ as COVID-19 spreads in other countries

B.C. takes over another Retirement Concepts senior care home

Summerland facility latest to have administrator appointed

Most Read