Drone photo of Park Bridge completed in 2015 in Kicking Horse Canyon shows challenge of highway widening through the Rocky Mountains. (Ministry of Transportation)

Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

Nelson’s Ryan Lewis wins main event at Fight Night 7

Lewis earned a split decision against Victoria’s Donny Cornelius

Warning issued after several overdoses in Castlegar

Interior Health says the overdoses appear to be the result of cocaine contaminated with fentanyl.

Leafs win seventh straight game

Nelson held off Golden 7-5

Green and NDP candidates talk strategic voting at Nelson public meeting

Wayne Stetski and Abra Brynne traded ideas but made no concessions for this election

Shawn Campbell scores 4 as Leafs beat Rebels 5-3

Campbell now has seven goals in just four games this season

More beef products recalled due to possible E. coli contamination

The food safety watchdog has been investigating possible E. coli 0157:H7

B.C. VIEWS: How to get the best deal on your ICBC car insurance

ICBC slowly being dragged into the 21st century

Pot legalization has gone ‘well’, but ‘yellow flags’ on vaping: task force chair

Canada legalized cannabis for non-medical use on Oct. 17, 2018,

ELECTION 2019: Federal leaders hit final 24 hours of campaign

Many leaders remain in B.C. for the final hours of the campaign

Jack’s Devils beat Quinn’s Canucks 1-0 in NHL brother battle

New Jersey youngster scores first career goal against Vancouver

Two charged after owner’s wild ride through Kamloops in his stolen truck

Crystal Rae Dorrington, 37, and Derrick Ronald Pearson, 32, facing multiple charges

Judge orders credit union’s bank records for Kelowna social worker facing theft allegations

The man is accused of negligence, breach of contract, fraud and a conspiracy with Interior Savings

Leaders pour it on with rallies, boosts for candidates as campaign reaches peak

The federal election campaign has reached a crescendo

Most Read