The first of two dormitory sections of the LNG Canada camp at Kitimat is now being assembled. (Photo courtesy LNG Canada)                                One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge. (Contributed photo)

The first of two dormitory sections of the LNG Canada camp at Kitimat is now being assembled. (Photo courtesy LNG Canada) One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge. (Contributed photo)

Workers’ camp at LNG facility in Kitimat takes shape

Extensive worker camp now being assembled

Born in Ireland but having spent years overseeing liquefied natural gas (LNG) construction projects in Australia, LNG Canada’s just-arrived general manager for its $40 billion facility in Kitimat is firm about his expectations.

“We want this to be the safest project on earth,” Vince Kenny says of construction which has just passed the one year mark leading to a planned finish in 2024.

With just under 1,000 people now working at the 400-hectare site, now is the time to cement that standard, he says.

“By the time we get to 5,000 people, we will have that culture in place,” Kenny emphasizes that this project which will be his seventh. “Unless we’ve got a culture, all the systems, processes and procedures are ineffective.”

Employees begin each shift reviewing the work plan, a procedure called a toolbox discussion.

“We’re here to take care of one another,” says Kenny, translating the IIF acronym that’s the hallmark of LNG Canada — Incident and Injury Free.

Even a brief tour of the works by a group of journalists from across B.C. starts with a video of LNG Canada workers outlining safety and security, the two words being almost interchangeable.

Workers have ID cards to be ‘badged in,’ creating an electronic record of their presence. They’re required to stay within their designated work area. There are constant security patrols. Vehicles are inspected for any fluid leaks before entry. There’s specific mention of drug-sniffing dogs too.

READ MORE: Okanagan company wins contract for LNG Canada project in Kitimat

No one gets on the site without basic safety equipment — hardhat, safety glasses, a high visibility vest, work boots and gloves. The driver of the tour bus taking the journalists to the site points out emergency exit windows. He brandishes a small hammer to smash a window if necessary. The bus doesn’t move until each passenger clicks in their seatbelt.

Victor Kenny, LNG Canada general manager

With Kenny is Trevor Feduniak who arrived in Kitimat in mid-2016. As the project site manager, he was one of the first senior LNG Canada people on location, overseeing the clearing of the former Methanex site and then expanding its footprint.

Although the project was not given the formal go-ahead until last October by LNG Canada’s investors Shell, PETRONAS from Malaysia, PetroChina from China, Mitsubishi Corporation from Japan and Korean-owned KOGAS, crews had been fully occupied raising up the location to a construction standard and to safeguard it against the possibility of tsunami sweeping inland from the Douglas Channel.

The fill comes from the nearby Sandhill, a mountain of material Feduniak describes as perfect for its material composition. One million cubic metres has already been transferred, edging away at the overall 2.5 million cubic metres that will have to be moved and placed in preparation for the arrival of two massive processing modules. From there, the gas will be transported via a pipeline from northeastern B.C., super-cooled to a liquid state for storage and then shipped out on specialized tankers to Asian customers.

“This is what we call coming out of the ground,” Feduniak explains as a tour bus winds its way through the site, encountering massive material-carrying trucks along the way.

Two streams that cross the site, the Kitimat Side Channel and Beaver Creek, were diverted to ensure Fluor-JGC has dry and stable conditions on which to construct the plant.

“When you disturb one habitat, you have to compensate with two [enhancement measures],” says Feduniak of the environmental work that was involved.

He compares the detailed water course replacement work for fish and other habitat to that of a landscaped Japanese garden.

One corner of the project site contains what, to the untrained eye, looks like sections of pipe stacked metres above the ground.

What they are are the pilings, 40 metres long, that will be driven into the ground upon which the two processing buildings will sit.

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

Those processing modules being built in Asia are to be 70 metres long, 35 metres wide and 50 metres tall, the approximate height of a 13-storey commercial building.

They’ll be shipped to Kitimat in modular segments and assembled on-site, being transported to their final resting place via an elaborate series of interconnected trailers with hundreds of wheels controlled by a single operator using a remote control. So sophisticated is the transport system that the operator is able to place the modules within centimetres of where they need to be located.

The sheer height of the modules has meant raising Rio Tinto BC Works’ power lines that cross the site to deliver power to the smelter from Kemano, so that the modules can fit comfortably underneath when being moved.

One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge, which is being built by the ATCO-Bird joint venture, for another joint venture between Fluor Corporation and JGC, the overall general contractor on the project.

There’ll be two living unit sections with a series of common buildings in the middle.

One of the modular accommodation sections is now being assembled with a finishing schedule of next spring to meet a first goal of 1,500 “heads in beds” with 1,000 more beds to be added each quarter thereafter to the final total of 4,500.

Unlike camps of past, each worker will have his or her own bathroom and each room will have its own TV. There’ll be sound dampening and other acoustic methods so that sleeping quarters will be as quiet as possible. The living areas will be co-ed.

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, an entertainment centre, a licensed lounge, a medical clinic, storage for luggage and housekeeping and maintenance facilities.

There’ll be landscaping around the area and informational material describes the facility as having the “largest core footprint” of its kind in Canada.

“You want your workers to come here and then want to come back,” said LNG Canada spokesperson Susannah Pierce of the atmosphere and amenities of the facility.

More than 4,500 people will be onsite at any one time at the peak of construction, requiring between 7,000 to 7,500 people in all given the shift work nature of the project. Workers will be onsite for 14 days at a time, returning after a seven-day break.

All this compares to another large worker camp in B.C. — the 1,600-room facility at B.C. Hydro’s Site C project in northeastern B.C.

With accommodation facilities now underway, there’s other activity on the waterfront at two terminal sites.

LNG Canada is building Rio Tinto a new wharf in exchange for taking over the aluminum smelting company’s existing wharf. Dredging is now going on as part of that project.

kitimatLNGlng canada

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

Just Posted

U.S. Senator Bernie Sanders sits in on a COVID-19 briefing with Dr. Bonnie Henry, provincial health officer, and Adrian Dix, B.C. minister of health. (Birinder Narang/Twitter)
PHOTOS: Bernie Sanders visits B.C. landmarks through the magic of photo editing

Residents jump on viral trend of photoshopping U.S. senator into images

Interior Health reported 79 new cases of COVID-19 and two new death in the region Friday, Jan. 22, 2021. (Ben Hohenstatt/Juneau Empire)
79 new COVID-19 cases, two deaths reported in Interior Health

Both of Friday’s deaths were both recorded at long-term care homes

Nelson Police responded to 802 calls last year they say had an element of mental health. File photo
Nelson Police: 802 mental-health related calls in 2020

That accounts for 12 per cent of total calls for service

Several large trees came down in the recent windstorm and destroyed a part of the building that houses Camp Koolaree’s showers and boy’s washroom. The camp has served generations of Kootenay families since 1931 as the Nelson area’s longest running children’s summer camp. Photo: Submitted
Camp Koolaree’s wash house destroyed by January windstorms

The camp is in need of donations to make repairs

U.S. Senator Bernie Sanders sits in on a COVID-19 briefing with Dr. Bonnie Henry, provincial health officer, and Adrian Dix, B.C. minister of health. (Birinder Narang/Twitter)
PHOTOS: Bernie Sanders visits B.C. landmarks through the magic of photo editing

Residents jump on viral trend of photoshopping U.S. senator into images

A 75-year-old aircraft has been languishing in a parking lot on the campus of the University of the Fraser Valley, but will soon be moved to the B.C. Aviation Museum. (Paul Henderson/ Chilliwack Progress)
Vintage military aircraft moving from Chilliwack to new home at B.C. Aviation Museum

The challenging move to Vancouver Island will be documented by Discovery Channel film crews

Cannabis bought in British Columbia (Ashley Wadhwani/Black Press Media)
Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

A video posted to social media by Chilliwack resident Rob Iezzi shows a teenager getting kicked in the face after being approached by three suspects on Friday, Jan. 22, 2021. (YouTube/Rob i)
VIDEO: Security cameras capture ‘just one more assault’ near B.C. high school

Third high-school related assault captured by Chilliwack resident’s cameras since beginning of 2021

FILE - In this Feb. 14, 2017, file photo, Oklahoma State Rep. Justin Humphrey prepares to speak at the State Capitol in Oklahoma City. A mythical, ape-like creature that has captured the imagination of adventurers for decades has now become the target of Rep. Justin Humphrey. Humphrey, a Republican House member has introduced a bill that would create a Bigfoot hunting season, He says issuing a state hunting license and tag could help boost tourism. (Steve Gooch/The Oklahoman via AP, File)
Oklahoma lawmaker proposes ‘Bigfoot’ hunting season

A Republican House member has introduced a bill that would create a Bigfoot hunting season

Economic Development and Official Languages Minister Melanie Joly responds to a question in the House of Commons Monday November 23, 2020 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
Federal minister touts need for new B.C. economic development agency

Last December’s federal economic update promised a stimulus package of about $100 billion this year

FILE - In this Nov. 20, 2017, file photo, Larry King attends the 45th International Emmy Awards at the New York Hilton, in New York. Former CNN talk show host King has been hospitalized with COVID-19 for more than a week, the news channel reported Saturday, Jan. 2, 2021. CNN reported the 87-year-old King contracted the coronavirus and was undergoing treatment at Cedars-Sinai Medical Center in Los Angeles. (Photo by Andy Kropa/Invision/AP, File)
Larry King, broadcasting giant for half-century, dies at 87

King conducted an estimated 50,000 on-air interviews

BC Coroners Service is currently investigating a death at Canoe Cove Marina and Boatyard in North Saanich. (Black Press Media File)
Drowning death in North Saanich likely B.C.’s first in for 2021

Investigation into suspected drowning Monday night continues

Kimberly Proctor, 18, was murdered in 2010. Her family has spent many of the years since pushing for a law in her honour, that they say would help to prevent similar tragedies. (Courtesy of Jo-Anne Landolt)
Proposed law honouring murdered B.C. teen at a standstill, lacks government support

Ministry of Mental Health and Addictions has concerns with involuntary detainment portion of act

Most Read